NJ American water will continue to push as efficiently as possible with their construction work. They have updated their schedule to the following:
7/8 - Saturday – Hubbard Avenue will be closed. – Water main will be filled and pressure tested.
7/10 - Monday – Hubbard Avenue will be closed. – The water main will be disinfected and tested. The concrete forms will be started.
7/11 - Tuesday – Hubbard Avenue will be closed. – South end will be tied in to the existing water main. Depending on when the test results from Monday come back they will tie in on the North side.
7/12 - Wednesday – Hubbard Avenue will be closed. – If the northern tie in was not completed, it will be done. The concrete pour for the supports will begin.
7/13 - Thursday – Hubbard Avenue will be closed. – The access pits for the concrete forms will be back filled.
7/14 - Friday – Hubbard Avenue will be closed. – The jersey barriers will be removed, and the guiderail will be put back.
7/15 - Saturday – Requesting one lane be closed on Hubbard. – The pipe insulation will be installed.
Any questions should be directed to NJ American Water at 1-800-272-1325. Thank you.