Middletown Recycling Center- Construction Updates

Construction Update as of 8/5/22:

Late-stage improvements continue at the Middletown Recycling Center on Kanes Lane!  All concrete work is complete as dumpster pads and curbs have been poured. Safety railings, fencing, and new gates have been installed and site drainage and electrical improvements were finished this week. The entire site will be re-graded and paved within the next 10 days. Stay tuned for an announcement on the Grand Opening date of our beautiful new and improved Recycling Center!


Recycling Center Image 1 8522
Recycling Center 2 8522
Recycling Center 3 8522
Recycling Center Main Image 8522



Construction Update as of 7/28/22:

Work continues on improvements at the Recycling Center. New concrete pads for dumpsters have been poured. Safety railings and new gates are being installed. The area for the new salt dome structure has been cleared. The contractor continues to grade the site in preparation for asphalt paving. 

20220727_14561120220727_145358

20220727_144933 20220727_145505   

Construction Updates as of 7/22/22:

The concrete work that constitutes the curb, pad and sidewalk has been completed. This pad will serve as the area for the Styrofoam, metal and electronic recycling. The electrical conduit is also complete. Materials have been brought in to raise the grade of the site which will allow for a more level surface area and improved drainage. The safety bollards are in the process of being installed along with the entry gates and surrounding fencing. 

20220722_08092320220722_080943

20220722_080855

20220722_081127


Construction Updates as of 7/13/2022:

The contractor has mobilized to the site and begun the demolition work necessary for the proposed improvements.  New concrete curbs and sidewalks have been poured.  New electrical conduit is being installed for the Styrofoam machine, security cameras, and building.  

20220714_09474320220714_094725

20220714_09471920220714_094757